New Central Private High School on Schedule For Completion August 1, Gym by October 1

Construction is well underway at Central Private School’s new campus at the corner of Joor and Gurney roads.  Head of school Robert Martin said the school is being built in three phases: Phase I – the new high school and gym, Phase II – the new elementary school and gym, and Phase III – other athletic facilities.

Bro. Martin said the new high school should be ready by August 1 and the gym by October 1.

He said fundraising is starting to pay for Phases II and III.  Anyone interested in donating should contact Katie Laurent at 225-261-3341.  Trade Construction founder Will Easley has said he too will help with fundraising.